The design was based on the recently updated corporate design guide. The main refurbishment was to the ground floor which consisted of full strip out and installation to include a reception area, multiple interview rooms and a staff breakout area. The new design included full decoration, and installation of new carpet and vinyl flooring throughout.
The remaining floors required a lower-level refurbishment/refresh. On level one a new staff breakout area was created, and the existing open plan workspace received a light touch refresh. The temporary interview space was stripped out and the area replaced with a staff conference room.
Both level two and basement areas received a light refresh.
Regarding the M&E package; a full rewire was carried out. The existing site housed old pyro installations that were replaced with new practices. New CAT6 data were supplied and installed to service the workstations.
New AC was installed throughout the ground and first floor with new ventilation.
Out of hours works were utilised alongside normal working hours to maintain the program and to allow the client to have full access to high priority meeting and interview rooms.